Louisiana Pacific Green Screen Upgrade and new Drying Facility

Louisiana Pacific Green Screen Upgrade and new Drying Facility

In July of 2017 Louisiana Pacific awarded FWM Mechanical the fabrication and mechanical installation of its Green Screen Upgrade and new Drying Facility.

FWM was selected to design, fabricate, and install 4000’ of 72” conveyors along with all associated diverter gates and transfer chutes.  In addition to material handling conveyors we will install 150 Tons of new structural steel.

As part of a very challenging retrofit to the Green Screen Upgrade, FWM will be installing six 90,000lb General Kinematic screens and vibratory transfer conveyors. 

The Dry Screening Process will be greenfield construction.  This installation includes two 90,000lb rotary dry screens and two vibratory secondary screens along with associated structural support steel and outfeed conveyors.

The project will begin September 2017 and complete in January of 2018.